1. IKE
Grant (North Kahler Road) Update:
The engineering
contract was received and is under legal review by City Attorney Urban and the 1st
kick off meeting will be after Dec 1st. There will be
neighborhood/community meeting scheduled in December and the most likely
location will by at Grace Lutheran Church. Engineer Zemaitis will keep us
posted. The survey crews will begin there site work as the first part of the
project engineering which will take about 2 weeks.
2. Building
Department Update – Building Inspector:
Joanne
Wagge accepted the part time building permit clerk open position and her hours
will be every Wednesday from 8:30 am to 11:30 am, also, Don Friddle accepted
the Building Inspector position (part time) and he will have hours on Wednesday
and as needed ($15.00 per hour and $50.00 per inspection).
3. ILLIANA
Update:
The next work study meeting will be December 6th
and a Public Meeting is scheduled for December 15th at the Matteson
Conference Center (Holiday Inn) from 4:00 pm to 7:00 pm, more information will
follow after the Dec 6th meeting.
4. The
Solar Compactor was installed and I was wrong on the location in my previous
emails. The location is south of Jackson Street not North.
5. Illinois
Transport did close on the JADA property on Monday, so the next city council
meeting and finance committee meeting the revised tax abatement schedule will
be on the agenda. The School District did revise their agreement last week and
Will County approved a 5 year tax abatement agreement last week. I will get
copies of these agreements to distribute next week.
6. Ridgeport
Water Tower foundation work began and the first concrete pour was today (Nov 23rd).
7. The
Miken Carthage (RT 53 & N. River Road site) Zoning hearing was completed at
the Planning Commission meeting and the Planning Commission did approve the B3
Zoning with a 4 Yes and 1 No vote. The Annexation Public Hearing is scheduled
for Dec 6th City Council Meeting. The revised annexation agreement
will be distributed next week which incorporated recommendations and
suggestions which were discussed at the Zoning Hearing. I will be visiting
their existing facility in McCook next week. There will be an open house forum
invitation for the public and elected officials to view the plans with Miken
Representatives at City Hall on Dec 6th at 5:30 pm before the
Administration Meeting.
8. Update
on the Solar Project on the JADA Site. ACCOINIA is moving forward with the
electrical connection study with Com Ed and this study should be completed by
Jan 1st and the next step will be to review the financial viability
of the project selling the power on the electrical energy market, mainly
working with the Illinois Power Authority to begin discussion for a Purchase
Power Agreement. This project still looks promising.
9. North
Island Christmas Walk displayed was inspected today and only a few minor
suggestions were indicated to cover the electrical connections with plastic and
secure the walk path lighting string. The Nativity Star was installed (by the
volunteers) as a fixed star instead of using any type of crane or boon to hang
the star overhead.
10. The
mower demonstration was a success and Supt VanDuyne will have more to report at
the WSSA committee meeting.
11. Staff
and the Wilmington Fire District had a emergency
weather preparation meeting last week to review the plan and resources
available to address snow removal and/or other weather related winter storm
emergencies. All the public works trucks have been inspected and repairs
completed for the snow plow equipment.