CITY OF WILMINGTON
1165 S. Water Street
Wilmington, IL 60481
815-476-2175
CITY ADMINISTRATOR
REPORT
10/14/2011
- RidgePort Logistics Business
Park:
The BNSF Rail Spur
construction continues with the electronic signalization being installed and
the rail crossing across of Lorenzo
Road will begin within the next 2-3 weeks. The
crossing will be closed while this work is being conducted and emergency
agencies and the school district are being notified. This project is being
coordinated through Will County Highway Department permit along with BNSF.
Widows Road Water
and Sanitary Sewer Main construction under I -55 is completed and service
connections to the 5 residents will begin. Landscaping coordination for the
screening on Widows Road south
of the Obrien Subdivision should begin within the next 2 - 3 weeks looks like
the length of this area is 350 feet and about 20 + trees will be installed.
Final restoration will begin in November with a follow up in the spring 2012.
- Proposed I
– 55 Interchanges for RT 129 and Lorenzo
Road:
IDOT will be
scheduling a follow up public meeting with the final alternatives within the
next 60 days and the official Public Hearing being planned for Spring 2012.
I – 55 - RT 129
Southbound Exit update the ramps are being removed and the overpass (bridge) is
planned to be removed Spring 2012. This exit will be
permanently closed until the new interchange is constructed.
- Continue
to work with IDOT on RT 53 request for a speed study from S. Arsenal Road
to Wilmington Peotone Road
with the goal to reduce the 55 mph speed limit into Wilmington. Also, further discussion
about the RT 53 & Wilmington Peotone Intersection improvements with further
updates being presented at the WSSA Committee meeting in November with a
presentation by HR Green Engineering Services – Transportation Proposal to
the City of Wilmington.
- Miken
Carthage Transportation has filed their annexation petition for the 7 acre
site located on the N/W corner of RT 53 and New River Road. The Planning
Commission concept review was completed at the 10/3/2011 meeting and the
company decided to move forward with formal application for annexation and
B3 Zoning. The company is planning on updating the current building on
site and will bring about 60+ jobs to the area some will be transfers from
their other locations and about 15 jobs will be new hires in the office
and truck mechanics. Their goal is to close on the property in January and
begin improvements immediately after the purchase. A schedule public
hearing is planned for the November 3rd Planning Commission
meeting.
- Illinois
Transport final plat was recommended for approval by the Planning Commission
on 10/3/2011. City Council approval is scheduled for 10/18/2011 City
Council meeting. The revised/amended real estate tax abatement agreement
will be presented at the 11/01/2011 City Council meeting. The company’s
profile and sample property tax bill with the current proposed tax
abatement amendment was distributed via email for the City Council to
review. Will County Tax Abatement agreement is moving forward through
their committees and is planned to be presented for approval at the
11/17/2011 County Board Meeting. The Wilmington School
District will be discussing their abatement
agreement at their next school board meeting. We will keep everyone
updated.
- The Widows Road
overlay street project will be coordinated with the MFT street improvement project and
construction should begin after 10/17/2011and completed within 2-3 weeks.
The two subdivision final lifts on their streets will be completed during
this timeframe for both Obrien Subdivision and Fox Tail Commons
Subdivision.
- The
electronic water meter project is 85% completed and the goal is to have
the change over of the remaining 15% completed within the next 30 days or
less. November 1st will begin the 30 day utility billing for
all zones within Wilmington.
- ‘IKE’
Grant update: The City received 17 RFQ responses for engineering services
and the preliminary reviews of their qualifications have been completed by
City Engineering Zemaitis and Administrator Graff. The final 3 engineering
firms will be interviewed and selection should be made by 10/22/2011. Tentative
schedule s for engineering to be completed by April 2012 and construction
during the summer months. The area for this project is the Kahler Road
and School District Property to address flooding problems.
- Water
Plant Intake and Facility upgrade work has begun and the divers should be
out in the river shortly. The Public Works crew has been assisting with
maintenance and labor upon request by Supt. Plese. The claricone filters
clean out will save an estimated $6,000 in labor costs as one of the first
phase of the project using City crew. Supt. Plese is keeping track of the
cost and will provide updates as the project continues to progress.
- Leak
Detection service has returned to complete the final work. There was a
minor delay with this project as the water atlas needed to be updated and
verified for the older part of the city so the project was done in phases.
Anticipate a report within the next 30 days.
- The
IEPA conducted an inspection of the water plant, distribution, storage
tanks, and well. The report will be completed and the City shall receive a
copy in about 45 days. Basically, the report will identify non-compliance
with the back flow prevention program (annual inspection report and
inventory records) and a program to exercise the water main valves
annually at least a multi-year zone program is recommended to open and
close the water valves at least once every 4 years. The goal by the IEPA
with non-compliance issues to allow the city time to come into compliance
before any enforcement action is recommended. As far as water facility
operations and quality water production, the inspector was impressed with
the current efforts and plans for facility upgrades.
- The
City Crew repaired a water main leak on Buchannan and the city water main
extended into the Winchester Plaza property, so the City crew was repairing
city water main not a private water main for the Winchester Plaza
property.
- The
City received a call about a sewer odor problem on Ridge and Buchanan area
and the crew located the sanitary sewer problem on Ridge St and repairs will begin with
the back up/broken city main.
- Next
meeting for the ILLANA work study group is 10/25/2011 to review the
environmental issues and corridor alignments. This meeting will be held in
Merriville IN. I will provide an update at the Nov 1st City
Council meeting. There will be another public informational meeting in
December location to be named.
- Concept
Plan review has been requested for 235 acres located on the southeast
corner of RT 53 and Coal City Road. I have had several meetings with the
property owner Mike Savage and he has prepared his request and
application. The concept plan review will be on the November 3rd
Planning Commission Meeting.
- Continue
to work with ITL (Kankakee
River Drive) and the owners are receiving bid
proposals to demolish the warehouse building on the N/W corner of their
site. Also, the grain transfer station concept is on hold at this time but
the owners are committed to continue to clean up their site.